Landowner guide

Is my land suitable for solar or battery storage?

What renewable energy developers look for in UK land, and how the deals work. Plain answers for landowners and farmers in England, Scotland, Wales and Northern Ireland.

The short answer

Developers look for land close to a part of the electricity network with spare capacity, on reasonably flat ground with road access, outside the most sensitive planning and flood areas, and not too close to homes. Battery storage can work on a few acres. Solar farms need more space. The single biggest factor is the grid connection.

1. Grid connection comes first

A project is only worth building if it can connect to the electricity network at a sensible cost and date. Developers look at the nearest substations and how much spare capacity they have.

  • Battery storage needs capacity in both directions. A battery draws power from the grid to charge (import) and sends it back to discharge (export). A substation can have plenty of export capacity but very little import capacity, which limits a battery.
  • Solar mainly needs export capacity, because it generates and sends power out during the day.
  • A line or pole on your land is a starting point, not proof. It shows where a connection might be made, not whether the network has room for a new project.
  • Published capacity figures are indicative. Network operators publish capacity maps, but only a formal response to a connection enquiry confirms what is available, what it costs and when.

The network operator depends on where you are: in Great Britain one of the regional distribution network operators, and in Northern Ireland NIE Networks.

2. How much land you need

  • Battery storage: compact. A few acres beside or near a substation can be enough.
  • Solar farms: larger. As a rough guide, ground-mounted solar uses around 4 to 6 acres per megawatt, so commercial schemes usually need tens of acres.
  • Onshore wind: open, exposed land in the right location, with good separation from homes.

Shape matters too. A compact field with room for a compound, access track and screening planting is easier to work with than a long, narrow strip.

3. Planning and environmental checks

  • Flood risk: equipment is kept out of the highest flood risk areas, so compounds go on drier ground.
  • Protected wildlife sites: SSSIs (ASSIs in Northern Ireland), Special Areas of Conservation and similar designations nearby need careful assessment.
  • Ancient woodland: development needs a buffer from ancient woodland. In England, Natural England's standing advice expects at least 15 metres.
  • Protected landscapes: National Landscapes (AONBs) and National Parks make planning more sensitive, though not always impossible.
  • Heritage: listed buildings and scheduled monuments nearby mean the setting has to be considered.
  • Farmland quality: the best and most versatile agricultural land gets more scrutiny, especially for large solar schemes.

4. Neighbours and access

Battery storage sites need noise assessment and fire safety separation from homes, and early contact with the local fire and rescue service. Every scheme needs safe access for construction vehicles from a public road.

5. How the money works

Most landowners choose one of two routes:

  • Lease: usually starts with an option agreement. The developer pays an option fee while it secures planning and a grid connection, then pays long-term, index-linked rent once the project is built. You keep ownership.
  • Sale: a capital sum now, from a buyer who takes the project forward.

What your land is worth depends mainly on the grid connection a developer can secure, the project size and the planning position. That is why a reliable figure needs the grid position first, and why competition between developers matters.

Questions landowners ask

Does a power line across my land mean it can host a battery or solar farm?

Not on its own. An overhead line shows where a connection might physically be made, but it says nothing about how much spare capacity the local network has. That depends on the substation the line comes from, and only the network operator can confirm it.

What is an option agreement?

A developer pays you an option fee for the right to take a lease (or buy the land) later, once planning permission and a grid connection are secured. You keep farming the land in the meantime. If the project does not go ahead, the option ends and the land stays yours.

Can I keep farming if I lease land for solar?

Often, yes. Many solar sites are grazed by sheep under the panels, and the rest of your holding is unaffected. The leased area is set out clearly in the agreement.

Does flood risk rule my land out?

Not automatically. Developers avoid putting equipment in the highest flood risk areas, so land in a flood zone usually needs a compound placed on drier ground and a flood risk assessment. The flood maps for England, Wales, Scotland and Northern Ireland are run by different agencies, so we check the right one for your area.

My land is in a protected landscape. Can it still be developed?

It is harder, but not always ruled out. National Landscapes (AONBs), National Parks and nearby heritage or wildlife sites make planning more sensitive, so these sites need a careful, early look at scale, screening and location.

Can I find out whether my land is suitable without paying?

Yes. Iris Property Group gives an initial view on your land at no cost and with no obligation. Tell us the location, size and access through our enquiry form.